Starting at the bottom of the roof map out a guideline with chalk.
Placing shingles on roof.
However make sure that you do not nail into the tar strip.
Get the right number of shingles for the job.
To start installing shingles line up aluminum drip edge flush with the edge of the roof and make a pencil line at the.
Use your chalk and tape measure to mark about 12 inches up on the roof for the first set of shingles.
Continue to chalk additional guidelines based on the width of the shingle through at least four courses rows across.
This saves a lot of time moving shingle bundles and a lot of back strain.
After completing a column the roofer can go back down to the eave edge of the roof and start laying the next column of shingles.
Lay a starting row at the bottom of the roof along the edge.
See below for a shopping list tools and steps subscr.
Place nails in the three tab shingles about 3 4 inch 1 8 centimeters above the cutouts near where the tab meets the upper part of the shingle.
Remove old shingles and.
Pull the drip edge down about a half inch from that line to.
What you need power nailer or roofing hatchet tape measure roofing shovel or flat pry bar hammer drill carpenter s square straight cut tin snips utility knife chalkline broom.
That s also why building codes commonly limit re roofing to no more than two layers.
Center a minimum 610 mm 24 wide minimum 28 gauge pre finished galvanized metal valley liner in the valley and fasten with only enough nails to hold it in place nailing at the edges only.
This will help determine how the shingles will lay on the.
Ask this old house general contractor tom silva reveals the best ways to secure shingles to a roof.
Measure the length of a shingle as it lies across the roof.
Installing roof shingles in 11 steps.
Installing new roof shingles over old effectively doubles the weight of the roofing so you have to make sure your roof structure can handle the extra load.
Using the chalk line snap a line between the two marks to get a straight edge.
Overlap each metal piece by at least 150 mm 6 and use asphalt plastic cement under each section of overlap.